ALL 12 of the Victorian enhancement sites between Beveridge and Albury (B2A) are now ready for the operation of double-stacked freight trains, which is a major milestone for Inland Rail.
The Tallarook passing loop was the last key site to be ready for the double-stack after being commissioned and out of action for six months; it returned to service earlier this week.
Passing loops are a parallel section of track that is connected to a single-track rail line that allows trains to safely pass or overtake each other.
A 1.15km section of the loop was lowered by 2.1 metres under the Hume Freeway to increase the vertical clearance without needing to rebuild the highway bridge higher. This involved removing 4000 tonnes of existing material and replacing it with 4000 tonnes of ballast, as well as laying 1650 new cross-ties (sleepers).
Works began on the B2A Tranche 1 project in March 2023, with the tracks being lowered and the bridges replaced at Seymour-Avenel Road, Glenrowan and Barnawartha North, and the railway station in Wangaratta was upgraded.
The B2A Tranche 2 project then began in June 2024 and is almost completed. Inland Rail and construction partner John Holland will continue the railway station transformations at Euroa and Benalla and are applying the finishing touches to the bridges in Broadford and Wandong.
Major bridge replacements or station upgrades at Wandong (Hume Freeway), Tallarook (Hume Freeway), Seymour (Hume Freeway), Broadford, Euroa and Benalla are due to be finished before the end of the year.
Inland Rail Chief Executive Officer Dr Sean Sweeney acknowledged how important reaching double-stack readiness at the main B2A sites is for them.
“The achievements on B2A come from a lot of hard work, consultation and cooperation with our contractors, stakeholders and local communities,” he said.
“We thank the local communities along the B2A alignment for their patience and understanding as we push to finalise all major works before the end of the year.”